  • 1.  collapsed spine

    Posted 10-18-2021 09:03
    I running a collapsed spine environment into two qfx5120-ym switches, in this we have L3 multihomed irb interfaces. When testing failover during a reboot of one of the switches an outage for irb interfaces of 10-16 seconds occure.
    Is there a way to set one of the switches in maintenance mode or certain configuration statements to minimize the outage?
    Regards
    /Tord